A full kitchen remodel typically takes three to six months from start to finish, and larger projects can stretch to eight months or longer. The building itself is only part of that. Planning, design and ordering often take as long as construction, so the kitchen is usually out of service for far less time than the whole project runs.
This guide walks through the kitchen renovation steps in order, with realistic time ranges for each phase. It also shows how to plan a kitchen design so decisions are made before they cost you money, and what causes most delays.
TL;DR
- Plan for 3 to 6 months from first design meeting to final touches for a full remodel. A cosmetic refresh can take 1 to 2 weeks.
- Planning and design take 1 to 3 months. Cabinet production is the longest wait when you order custom.
- Lock your layout, cabinets and appliances before demolition. Changing your mind mid-project is the most common homeowner-caused delay.
- Order materials while permits are processed, and stage everything before the first wall comes down.
- In-stock materials shorten the schedule. We deliver in-stock items in Central Florida in 24 to 48 hours.
Table of Contents
- How long a kitchen remodel really takes
- The kitchen renovation steps in order
- Cosmetic refresh, full remodel or gut renovation
- What causes kitchen remodel delays
- Kitchen and bath at the same time
- Our perspective
- Plan your Orlando kitchen with us
- FAQ
- Sources
How long a kitchen remodel really takes
The honest answer is a range, and it depends on scope. The table below shows the three most common project types, using figures from published remodeling data.
| Project type | Typical timeline | Source |
|---|---|---|
| Cosmetic update (paint, hardware, minor swaps) | 1 to 2 weeks | U.S. News Real Estate |
| Average kitchen remodel | 4 to 8 weeks of work | U.S. News Real Estate |
| New layout, new appliances, structural changes | 2 to 3 months | U.S. News Real Estate |
Bob Vila, citing the Zonda Media 2024 Cost vs. Value Report, puts minor kitchen remodels at 3 to 4 weeks, compared with 10 or more weeks for a major remodel.
There is also the time before work starts. The 2024 U.S. Houzz & Home Study found kitchens had the longest timeline of any room in 2023, with an average of 9.6 months of planning and 5.1 months of building. The 2026 study reports that homeowners who renovated in 2025 averaged 9.5 months of planning and 5.8 months of construction.

Those are averages across all kinds of homeowners, including people who pause to save money or take a long time choosing. A prepared homeowner with a clear budget can move much faster.
The kitchen renovation steps in order
Here is the sequence most projects follow. USA Today's phase-by-phase breakdown gives these ranges: planning and design 1 to 3 months, layout, plumbing and electrical work 1 to 3 weeks, cabinet installation 1 to 2 weeks, countertops 2 to 4 weeks, appliances 1 to 3 or more weeks, and flooring 3 to 7 days. Custom cabinet production and delivery is listed at 8 to 20 or more weeks.
| Phase | Typical time |
|---|---|
| Planning and design | 1 to 3 months |
| Cabinet ordering (custom production and delivery) | 8 to 20+ weeks |
| Layout changes, plumbing, electrical | 1 to 3 weeks |
| Cabinet installation | 1 to 2 weeks |
| Countertop fabrication and installation | 2 to 4 weeks |
| Appliance delivery and installation | 1 to 3+ weeks |
| Flooring | 3 to 7 days |
Some phases overlap. Cabinets are ordered while design is finishing or permits are processing, so the total is not the sum of every row.
Step 1: Set your budget and goals
Before you talk to anyone, write down three things: your budget, what bothers you about the current kitchen, and what you cannot live without. This takes a few days and saves weeks later. A clear budget tells you whether you are doing a refresh, a full remodel or a layout change.
Also decide who is doing the work. Many homeowners hire a general contractor and trades. Others, including DIYers, handle some tasks themselves, such as cabinet assembly or flooring, to save money. Be realistic about your free time, because weekend work stretches a schedule.
Step 2: Design and plan the layout
This is the kitchen design process that sets the rest of the schedule. You choose the layout, cabinet style, countertop material, flooring, sink, faucet, lighting and appliances. You also take measurements and confirm where plumbing, gas and electrical will go.
Get help early, especially if you are moving anything. A source summarizing National Kitchen and Bath Association guidance says an early designer matters most when the layout changes, because those decisions lock in where plumbing and electrical rough-in goes, and changing them later is expensive.
A 3D design makes this stage faster. You can see the layout, check walkways and compare cabinet colors before you buy anything. We offer a free 3D kitchen design so you can settle the plan before you order.
One more design point: the 2026 industry reporting notes that cabinet lead times were moderating but some major appliances had longer waits. That makes it smart to pick appliances early, since their exact dimensions affect cabinet sizes and cutouts.
Step 3: Hire your team and get bids
A typical team includes a designer, a licensed general contractor and specialty trades. A detailed written contract should cover the scope, drawings, milestone dates, change-order procedures, warranties and lien-release requirements, with payments tied to completed milestones you can inspect.
We supply materials and design guidance rather than doing construction ourselves. If you need installers, we refer homeowners to independent installation professionals. Contractors and builders can also look at our wholesale cabinets for contractors.
Allow a few weeks for bids and scheduling. Good trades are often booked ahead, so ask for start dates when you collect bids.
Step 4: Permits
Permits depend on your city or county. Moving walls, plumbing or electrical circuits usually needs one, while swapping cabinets and countertops often does not. Ask your contractor, or call your local building department, which applies to your project. Processing times vary by jurisdiction, so get the current estimate from them.
A good rule is to submit permits only after the layout is final. A change after submission can mean revised plans and more review time.
Step 5: Order materials
Ordering is where schedules are won or lost. Cabinets are the biggest variable: custom cabinet production and delivery runs 8 to 20 or more weeks, while in-stock lines can be on your driveway within days.
That is why we stock RTA kitchen cabinets and offer 24 to 48 hour delivery on in-stock materials. If you are in Orlando, see our kitchen cabinet delivery in Orlando page. Countertops need a template after the cabinets go in, then fabrication, so build that into your calendar. Our quartz countertop fabrication page explains that process.
Stage everything before demolition. Confirm each box, slab and appliance is the right item, in the right size, and not damaged. Consumer Reports found almost one-third of contractors reported delays from materials arriving damaged or the wrong item shipped.
Step 6: Demolition and rough-in
Old cabinets, counters and flooring come out, usually in a few days. If walls are opening up, plumbers and electricians do rough-in work next, typically one to three weeks depending on scope. Any required inspections happen here, before walls are closed.
Set up a temporary kitchen first: a microwave, a small fridge, a hot plate and a folding table in another room. Plan for paper plates and takeout. It is easier on the family than improvising on day three.
Step 7: Walls, flooring and paint
Drywall, patching, paint and floor prep come next. Flooring can go in before or after cabinets, depending on the plan, so ask your installer. Waterproof SPC, WPC and luxury vinyl plank install quickly, often in a few days for a typical kitchen. See our flooring options if you are comparing materials for a Florida home.
Step 8: Cabinets, countertops and fixtures
Cabinet installation takes one to two weeks. Then comes the countertop template, fabrication and install, which together take two to four weeks. Plumbing hookups, backsplash, hardware, lighting and appliances follow.
The countertop gap is the part that surprises people. You have base cabinets but no counters for a while. Plan for it rather than fighting it.

Step 9: Punch list and final walkthrough
Walk the kitchen with your contractor and note everything that needs fixing: paint touch-ups, door alignment, caulk lines, a missing outlet cover. Do not make the final payment until the list is done.
Cosmetic refresh, full remodel or gut renovation
Your scope changes everything. A useful way to think about it:
- Cosmetic refresh: new paint, hardware, faucet, maybe a backsplash or new flooring. One to two weeks of work, with little or no waiting on custom orders.
- Mid-range remodel, same layout: new cabinets, counters, flooring and fixtures where the old ones were. A few weeks of work after materials arrive, so ordering speed decides the total.
- Gut renovation with layout changes: walls, plumbing and electrical move. Expect permits, inspections and the longest overall schedule, with construction in the range of two to three months or more.
If your budget is tight, keeping the existing layout is the biggest schedule saver. Sinks, gas lines and drains stay put, so there is less rough-in work and fewer inspections.

What causes kitchen remodel delays
Consumer Reports found that in a 2016 nationally representative survey of 1,012 homeowners, 29 percent of remodelers said their projects took longer than they expected. The same article reports contractors citing these causes:
- Unforeseen structural damage: 42 percent of contractors named it as the leading reason for falling behind.
- Client changes: 60 percent said the biggest client mistake was changing their mind mid-construction.
- Wrong or damaged materials: almost a third reported delays from items arriving damaged or incorrect.
Hidden problems are the one you cannot fully control. A contractor in USA Today notes that once walls open, concealed beams, wiring or plumbing can reveal extra work. Keep a buffer of a couple of weeks and some money for it.
Supply is another factor. An architect quoted in the same USA Today piece says many construction materials are imported, and rising costs and tariffs can mean longer delays getting them. Ordering early and choosing in-stock items reduces that exposure.
The electrical side can also surprise you. A home inspector quoted by Consumer Reports points out that inspectors can help during a remodel, for example by identifying a kitchen circuit that needs upgrading to power an induction range. Finding that before demolition is much cheaper than finding it after.
How to keep your schedule on track
- Finalize every selection before demo. Cabinets, counters, sink, faucet, flooring, lighting and appliances.
- Run permits and ordering in parallel. Do not wait for approval to place the cabinet order if your lead time is long.
- Stage materials. Have them delivered and checked before work begins.
- Book trades ahead. Ask each one for a start window tied to the previous phase.
- Add a buffer. Two weeks on a mid-size project is reasonable.
- Put changes in writing. Use change orders so everyone knows the cost and time impact.
Kitchen and bath at the same time
Many Central Florida homeowners renovate both rooms together. It can save on contractor mobilization, but it doubles your decisions. If the bathroom is on your list, our bathroom renovation timeline shows how long each stage takes, and this bathroom remodel timeline lays out three schedules you can compare. Vanities usually arrive faster than full cabinet runs, so the bath can often be done first as a warm-up.
Our perspective
Most kitchen delays we see start at the same place: a long wait for cabinets, or a selection changed after the order. The fix is to pick a plan you are sure about and choose materials that are available when you need them.
That is how we built Sunshine Home Material. We are a family-owned showroom and design center in Orlando, and we sell factory-direct RTA cabinets, stone and quartz countertops, waterproof flooring, vanities and hardware at pricing designed to be affordable. In-stock items can be delivered in 24 to 48 hours, which takes the longest wait out of many schedules.
We also help you decide before you buy. Our free 3D design lets you see the layout, and our team can walk you through cabinet, countertop and flooring choices in the showroom, so your selections are final before the contractor starts. That is the single most useful thing you can do for your timeline.
Sunshine Home Material
Plan your Orlando kitchen with us
If you are planning a kitchen in Orlando, Winter Park, Lake Mary or elsewhere in Central Florida, we can help you line up the materials side of the schedule. We offer free 3D kitchen and bath design, project estimates, RTA and assembled cabinets, stone countertops, flooring, delivery and warehouse pickup. Financing is available for qualified buyers, and we can refer you to independent installers.

Start with our kitchen and bath remodeling in Orlando page, browse our RTA kitchen cabinets, or contact us for a design consultation.
FAQ
How long does a kitchen remodel take?
A full remodel typically takes three to six months from the first design meeting to completion, according to USA Today. Active construction is often 4 to 8 weeks for an average project. Cosmetic updates can take one to two weeks.
How far ahead should I start planning?
Start as soon as you are serious, ideally several months before you want demolition to begin. Planning and design commonly take one to three months, and custom cabinets can add many more weeks. Choosing in-stock cabinets shortens the wait.
Can I live in my house during a kitchen remodel?
Most people do. Set up a temporary kitchen with a microwave, small fridge and basic supplies in another room. Expect the kitchen to be unusable for several weeks, mainly during demolition, cabinet install and the countertop gap.
What is the best order for kitchen renovation steps?
Budget and goals, design, hiring and bids, permits, ordering, demolition, rough-in, walls and flooring, cabinets, countertops and fixtures, then the final walkthrough. Ordering overlaps with design and permits so you are not waiting on deliveries.
Sources
- USA Today: How long does a kitchen remodel take?
- U.S. News Real Estate: How Long Does a Kitchen Remodel Take?
- Bob Vila: Sweet Spot Kitchen Remodel
- 2024 U.S. Houzz & Home Study
- CCR Magazine: A Practical Guide to Planning and Managing a Kitchen Renovation
- Consumer Reports: How to Remodel on a Budget and Stay on Schedule
- Fin Home Contracting: Kitchen Remodel Timeline, Phase by Phase
- Bathroom Remodel Timeline for Homeowners